Data as of: August 31, 2026Updated: September 14, 2026505 records
- Approved Budget
- $3,198,901,717.98
- Adjusted Budget
- $4,446,448,399.27
- Total Expenditures
- $694,318,579.96
- Budget Balance
- $3,752,129,819.31
Departments in Department of Transportation
505 departments in Department of Transportation. Click a department to drill into its funds.
All Budgets · FY2027 · Executive
Filters
| Department | Funds | Approved Budget | Adjusted Budget | Total Expenditures | Budget Balance |
|---|---|---|---|---|---|
| All | 17 | $3,198,901,717.98 | $4,446,448,399.27 | $694,318,579.96 | $3,752,129,819.31 |
| LOS ALAMOS CO N MESA LAPS LAND | 1 | $1,154,000.00 | $1,154,000.00 | $0.00 | $1,154,000.00 |
| N I-25 INTERCHANGE CONSTRUCT | 1 | $1,100,000.00 | $1,100,000.00 | $0.00 | $1,100,000.00 |
| DONA ANA CO SALEM DRAIN PH 1 I | 1 | $1,088,000.00 | $1,088,000.00 | $0.00 | $1,088,000.00 |
| PASEO DEL NORTE & UNSER BLVD E | 1 | $1,073,774.53 | $1,073,774.53 | $0.00 | $1,073,774.53 |
| PASEO DEL VOLCAN CONSTRUCT | 1 | $1,048,000.00 | $1,048,000.00 | $0.00 | $1,048,000.00 |
| BERN CO MTN VIEW NBRHD DRAIN C | 1 | $1,000,000.00 | $1,000,000.00 | $0.00 | $1,000,000.00 |
| ENGLER RD CONSTRUCT | 1 | $1,000,000.00 | $1,000,000.00 | $0.00 | $1,000,000.00 |
| I-10 RAMPS IMPROVE | 1 | $1,000,000.00 | $1,000,000.00 | $0.00 | $1,000,000.00 |
| L25, 1S, C160-S5-I238 | 1 | $1,000,000.00 | $1,000,000.00 | $0.00 | $1,000,000.00 |
| N I-25 INTERCHANGE CONSTRUCT | 1 | $1,000,000.00 | $1,000,000.00 | $0.00 | $1,000,000.00 |
| US HWY 285/MILL RD INTRSECT SI | 1 | $1,000,000.00 | $1,000,000.00 | $0.00 | $1,000,000.00 |
| HURLEY RDS & DRAIN IMPROVE | 1 | $960,000.00 | $960,000.00 | $0.00 | $960,000.00 |
| SUN RANCH VILLAGE RD & DESERT | 1 | $950,000.00 | $950,000.00 | $0.00 | $950,000.00 |
| SANTA CLARA ROAD & DRAINAGE IM | 1 | $940,000.00 | $940,000.00 | $0.00 | $940,000.00 |
| L21 2SS C4 S2 IP | 1 | $920,849.00 | $920,849.00 | $920,849.00 | $0.00 |
| PINE LODGE RD CONSTRUCT | 1 | $900,000.00 | $900,000.00 | $900,000.00 | $0.00 |
| 4TH STREET CONSTRUCT | 1 | $850,000.00 | $850,000.00 | $0.00 | $850,000.00 |
| DONA ANA CO SIDEWALKS PH 3 CON | 1 | $850,000.00 | $850,000.00 | $90,103.63 | $759,896.37 |
| ZENITH CT NE ACCESS POINT CONS | 1 | $850,000.00 | $850,000.00 | $12,760.03 | $837,239.97 |
| ANTHONY STREETS IMPROVE | 1 | $800,000.00 | $800,000.00 | $0.00 | $800,000.00 |
| GATEWOOD AVE SW CONSTRUCT | 1 | $800,000.00 | $800,000.00 | $0.00 | $800,000.00 |
| N30/US HWY 491 LIGHT CONSTRUCT | 1 | $800,000.00 | $800,000.00 | $0.00 | $800,000.00 |
| ROSWELL STORM DRAIN BRASHER RD | 1 | $800,000.00 | $800,000.00 | $555,970.06 | $244,029.94 |
| SAN PEDRO DR NE STREETSCAPE RE | 1 | $800,000.00 | $800,000.00 | $0.00 | $800,000.00 |
| DONA ANA CO E MESA FLOOD CONTR | 1 | $775,000.00 | $775,000.00 | $209,895.68 | $565,104.32 |